UK-based Hurricane Energy has finished the well completion for the Lancaster field, and the production wells are now set to be tied-in to the subsea infrastructure. Apart from well completion of the Lancaster EPS, where first oil is expected in 2019, installation of the mooring system for FPSO and installation of SURF are also on Hurricane’s list for this summer. The mooring system installation is currently underway, offshore UK.
UK-based Hurricane Energy has said that the company has started well completion of its 500 million barrel capacity Lancaster early production system (EPS). Well-operator, Petrofac will be using Paul B. Loyd Jr. harsh environment semisubmersible rig for completion operations. The third quarter of 2018 will see the installation of Aoka Mizu floating production, storage and offloading vessel (FPSO) at the field. The Lancaster Production will begin next year.